Restoration - After Three Weeks
Between Clay and Albert the restoration team were very busy during the the third week.
In the main auditorium a lot more of the rubble has been sorted and many bricks prepared for reuse.

The Baptistry is taking shape ...


The donated pallisade has been brought to the church ...

Work has been done on repairing the auditorium windows that were bricked in ...

Work has also been done on the two classrooms and bathroom ...
Bathroom straight at end of coridoor. The bathroom is being split into two to accommodate a Mens and a Ladies bathroom.
Classroom 1 to right, and classroom 2 to left. The classroom to the left's door is being bricked up, and an the door being moved so that access will be from the room behind the coridoor wall to the left. See picture below.

The new door for classroom two. The coridoor is behind the wall to the right of the new door.

The veranda (previously a side entrance to the building), now being turned into a study progressed as well ...
The door into the kitchen area from the former veranda has been blocked up ...

The inner window in the study has been blocked up ...

In the kitchen ...
The cupboards and counter shows visible progress ...

The new geyser was fitted ...

And then last of all, the trench in the back yard has been filled with a leaky water pipe repaired!

Good going team!